Line 23: | Line 23: | ||
Expect to finish restringing the above 33 wires in 2-3 weeks. | Expect to finish restringing the above 33 wires in 2-3 weeks. | ||
+ | |||
+ | Thursday (5pm -> 7pm), Friday (8:30 am -> 4pm), Saturday (9am->4pm) | ||
[[CLAS12_R1_Progress_Reports]] | [[CLAS12_R1_Progress_Reports]] |
Revision as of 16:18, 18 October 2013
10/18/2013
Current total loose wires we need to fix (try pulling on the pin) on both chambers combined (our only uncertainty in how many additional replacements there could be):
6
Current total known replacement wires that need to be done:
S2: 17 wires; 6 field, 11 sense SL1 - 6 field, 9 sense SL2 - 2 sense
S3: 16 wires; 14 field, 2 sense SL1 - 10 field, 1 sense SL2 - 4 field, 1 sense
Total wires left to replace between both chambers: 33
S2 is aligned for stringing on SL2 - 2 wires left to string on this superlayer before we need to re-align. S3 is aligned for stringing on SL1 - 11 wires left to string on this superlayer before we need to re-align.
Expect to finish restringing the above 33 wires in 2-3 weeks.
Thursday (5pm -> 7pm), Friday (8:30 am -> 4pm), Saturday (9am->4pm)