Difference between revisions of "201304 R1ProgressRep"

From New IAC Wiki
Jump to navigation Jump to search
Line 55: Line 55:
  
 
began at 7:35am, icy roads
 
began at 7:35am, icy roads
 +
 +
 +
=4/11/13=
 +
 +
Dion: took a vacation day
 +
 +
David: String both chambers with Debbie
 +
 +
Debbie: String with David
 +
 +
Haitham: Q&A documentation of signals on S6
 +
 +
Carlos: restored cosmic test stand PMTs and start to take R1 S1 data with ADB crate
 +
 +
  
 
[[CLAS12_R1_Progress_Reports]]
 
[[CLAS12_R1_Progress_Reports]]

Revision as of 18:51, 12 April 2013

4/1/13

Dion: Will start stringing S3 Field with David at 10 am ,HV test the Cracken

David: String S3 Field with Dion , document pulses from S6 until DIon arrives

Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon

Haitham: String S2 with Debbie

Carlos: Wire tension measurements & CHECK ADB Polarity use STB + pulse generator to inject signals and test ADC->TDC channels

4/4/13

Dion: stringing S3 Field with David at 10 am ,finished the Cracken cable

David: String S3 Field with Dion , work on ADB crate with Carlos

Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon

Haitham: String S2 with Debbie

Carlos: Wire tension measurements & CHECK ADB Polarity use STB + pulse generator to inject signals and test ADC->TDC channels


Stopped work at 5pm


4/8/13

Dion: stringing S3 Field with David at 10 am ,install & test the Cracken cable

David: String S3 Field with Dion , work on ADB crate with Carlos

Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon

Haitham: String S2 with Debbie

Carlos: Wire tension measurements & test ADC->TDC channels

began at 7:35am


4/9/13

Dion: stringing S3 Field with David

David: String S3 Field with Dion

Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon

Haitham: String S2 with Debbie

Carlos: Wire tension measurements & restore cosmic test stand PMTs

began at 7:35am, icy roads


4/11/13

Dion: took a vacation day

David: String both chambers with Debbie

Debbie: String with David

Haitham: Q&A documentation of signals on S6

Carlos: restored cosmic test stand PMTs and start to take R1 S1 data with ADB crate


CLAS12_R1_Progress_Reports