Difference between revisions of "201303 R1ProgressRep"
(5 intermediate revisions by 2 users not shown) | |||
Line 114: | Line 114: | ||
Carlos: Wire tension measurements & use STB + pulse generator to inject signals and test ADC->TDC channels | Carlos: Wire tension measurements & use STB + pulse generator to inject signals and test ADC->TDC channels | ||
+ | |||
+ | =3/27/13= | ||
+ | |||
+ | Dion: String S3 Field with David , continue ribbon HV cable (the Cracken) | ||
+ | |||
+ | David: String S3 Field with Dion , use STB + pulse generator to inject signals and test ADC->TDC channels | ||
+ | |||
+ | Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon | ||
+ | |||
+ | Haitham: String S2 with Debbie | ||
+ | |||
+ | Carlos: Wire tension measurements & use STB + pulse generator to inject signals and test ADC->TDC channels | ||
+ | |||
+ | Confirmed mapping of ADB input channels on front to ECL output on the back: | ||
+ | |||
+ | {| border="1" |cellpadding="20" cellspacing="0 | ||
+ | |- | ||
+ | | Input || Output | ||
+ | |- | ||
+ | | 1-16 || 1-16 | ||
+ | |- | ||
+ | | 17-24 || 17-24 | ||
+ | |- | ||
+ | | 49-56 || 25-32 | ||
+ | |- | ||
+ | | 81-96 || 33-48 | ||
+ | |- | ||
+ | |||
+ | |} | ||
[[CLAS12_R1_Progress_Reports]] | [[CLAS12_R1_Progress_Reports]] |
Latest revision as of 21:34, 27 March 2013
3/4/13
Dion: String S3 with David
David: Stringing S3 Guard
Debbie: String S2 in the morning, HV burn in S6 in the afternoon
Haitham: String Guard on S2
Carlo: HV burn in & signal search S6
Progress:
A super layer of guard wires has been strung on both S2 & S3.
Should be finished with Guard wires by next week
3/5/13
Dion: String S3 with David
David: Stringing S3 Guard
Debbie: String S2 in the morning, HV burn in S6 SL2-HVB6 in the afternoon
Haitham: String Guard on S2
Carlo: HV burn in SL2-HVB6
3/7/13
Signals observed on all channels of S2 SL2 HVB5.
3/11/13
Dion: String S3 Field with David
David: Stringing S3 Field
Debbie: String S2 in the morning, HV burn in S6 SL2-HVB5 in the afternoon
Haitham: String Field S2
Carlo: HV burn in SL2-HVB5
3/18/13
Dion: String S3 Field with David
David: Stringing S3 Field
Debbie: String S2 in the morning, Look for signals on STB5
Haitham: String Field S2
Carlos: Wire tension measurements & ADB crate checkout
3/19/13
Dion: String S3 Field with David
David: Stringing S3 Field
Debbie: String S2 in the morning, Debbie needs time off after lunch
Haitham: String Field S2
Carlos: Wire tension measurements & ADB crate install
3/20/13
Dion: String S2 Field with David
David: String S2 with Dion
Debbie: sick day Haitham: Look for signals on S6 then String Field S2 when Debbie arrives
Carlos: Wire tension measurements & ADB crate install
3/21/13
Dion: String S3 Field with David
David: String S3 with Dion
Debbie: String S2 Field
Haitham: String Field S2
Carlos: Wire tension measurements & ADB crate install
3/25/13
Dion: String S3 Field with David , finish 2nd HV octopus & install on S1, continue ribbon HV cable
David: String S3 Field with Dion , use STB + pulse generator to inject signals and test ADC->TDC channels
Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon
Haitham: String S2 with Debbie
Carlos: Wire tension measurements & use STB + pulse generator to inject signals and test ADC->TDC channels
3/26/13
Dion: String S3 Field with David , continue ribbon HV cable
David: String S3 Field with Dion , use STB + pulse generator to inject signals and test ADC->TDC channels
Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon
Haitham: String S2 with Debbie
Carlos: Wire tension measurements & use STB + pulse generator to inject signals and test ADC->TDC channels
3/27/13
Dion: String S3 Field with David , continue ribbon HV cable (the Cracken)
David: String S3 Field with Dion , use STB + pulse generator to inject signals and test ADC->TDC channels
Debbie: String S2 Field with Haitham, Document S6 signals in the afternoon
Haitham: String S2 with Debbie
Carlos: Wire tension measurements & use STB + pulse generator to inject signals and test ADC->TDC channels
Confirmed mapping of ADB input channels on front to ECL output on the back:
Input | Output |
1-16 | 1-16 |
17-24 | 17-24 |
49-56 | 25-32 |
81-96 | 33-48 |