Difference between revisions of "201204 R1ProgressRep"
Line 238: | Line 238: | ||
Strung 63 Field wires through row 17 SL2. | Strung 63 Field wires through row 17 SL2. | ||
+ | |||
+ | =4/12/12= | ||
+ | |||
+ | Strung 21 Field wires through row 21 SL2. Reattached clean room wall and shifted it to allow more room. Before and after pictures to be uploaded soon. |
Revision as of 21:42, 12 April 2012
4/2/2012
Started stringing SL1. Strung 48 guard wires, now on row 45 SL1.
R1 S1 sense wire signals
4/3/2012
Column is high number
Continued stringing SL1 guard wires. Strung 35 wires, now on row 80.
Soldered more stringing chains.
4/4/12
HVB-2
Strung 75 Guard wires (now on row 156).
4/5/12
Mounted Chamber 5 on A-Frame. Strung 44 guard wires through row 200.
4/6/12
Mounted magnet and stringing rail on Chamber 5. Strung 33 guard wires finishing guards on Chamber 6.
4/9/12
Visual inspection of Ch 6 Guard wires complete. Ready to start stringing Field wires tomorrow.
Mounted stringing arm and stringing machine on Ch 5. Ch 5 ready for stringing.
4/10/12
Aligned Ch 6 for SL2 stringing. Strung 36 Field wires through row 7.
4/11/12
Strung 63 Field wires through row 17 SL2.
4/12/12
Strung 21 Field wires through row 21 SL2. Reattached clean room wall and shifted it to allow more room. Before and after pictures to be uploaded soon.