+ | === 10/1/10=== | ||
+ | |||
+ | Install HRRL cavity mounting system | ||
+ | |||
+ | === 10/4-6/10=== | ||
+ | |||
+ | Disassemble beam line and move HRRL cavity to new location | ||
+ | |||
+ | ===10/7-14/10=== | ||
+ | |||
+ | ;Alignment | ||
+ | |||
+ | A lot of time is being allocated to align the accelerator | ||
+ | |||
Khalid, Sadiq, and IAC theodolite operator. | Khalid, Sadiq, and IAC theodolite operator. |
Revision as of 15:07, 2 September 2010
Timeline
Start Date | Finish Date | Task |
10/01/10 | 11/01/10 | Move the HRRL and construct new beamline |
11/01/10 | 11/15/10 | Measure Radiation Field and Prepare for Hunt Run |
11/15/10 | 12/17/10 | Hunt Beam Time (3 MeV, 300 Hz, multiple pulsing) |
01/03/10 | 01/14/10 | Prepare for high current emmittance measurements |
01/18/10 | 01/21/10 | high current emmittance measurements (10 MeV, 50 ns pulse width, variable rep rate and current) |
Tasks
Design and build required infrastructure
Beam line CAD
The location of all magnets is provided by Yujong Kim.
Kevin Folkman will layout the CAD drawings
Accelerator Wall Mount
A mounting system needs to be designed for the HRRL which will be used for its new position. It is unclear if we can reuse the current stands. We will want a way to add lead sheets around the HRRL and the location of the Tungsten converter target which is after the first 3 quads and labeled (PT) in the drawings.
Stands
Chad has built one stand to hold 3 Quads. We will need 3 more stand built to hold quad triples and 2 stands to hold the "Kiwi" dipoles.
FC cooling
We need to solder cooling lines around the FC.
Move the HRRL
10/1/10
Install HRRL cavity mounting system
10/4-6/10
Disassemble beam line and move HRRL cavity to new location
10/7-14/10
- Alignment
A lot of time is being allocated to align the accelerator
Khalid, Sadiq, and IAC theodolite operator.
1.) Alignment:
a.) spare gun
b.) laser with targets mounted on wall.
Design preference
Thin aluminum target for OTR right after 3 quads place at exit to Linac