| (mm) ||  plastic || metal
 
|-
 
{
 
 
|-
 
|-
 
|Beam setup || 0.5 days
 
|Beam setup || 0.5 days

Revision as of 22:44, 27 April 2009

http://clasweb.jlab.org/wiki/index.php/Hall_A_IAC_Tests


Previous Tests: IAC_LeadFlourideCherenkovCrystalTests

Run Plan

Summary

Task Time Budget
Beam setup 0.5 days
Testing 20 new blocks 2.5 days
Silicon test 1.0 day
Bleaching/Re-irradiation test 0.5-1 day
Testing old blocks 12 blocks/day

5/11/09