Difference between revisions of "Mini-prototype"
Jump to navigation
Jump to search
Line 4: | Line 4: | ||
=== General Operating Condition=== | === General Operating Condition=== | ||
− | Our initial plan will be to use <math>ArCO_2</math> (75/25) flowing though the chamber | + | Our initial plan will be to use <math>ArCO_2</math> (75/25) flowing though the chamber at a rate to exchange the volume once a day. A CAEN 4 channel high voltage supply (N495) will be used to supply HV for the drift chambers. The supply is capable of monitoring currents at the microamp level. |
describe gas used, HV, signal electronics | describe gas used, HV, signal electronics | ||
+ | |||
==Cosmic tests== | ==Cosmic tests== | ||
===scope pulses=== | ===scope pulses=== |
Revision as of 23:27, 17 August 2007
Drift Chamber prototypes were constructed to evaluate drift chamber designs for CLAS12
Mini-prototype Performance Measurements
General Operating Condition
Our initial plan will be to use
(75/25) flowing though the chamber at a rate to exchange the volume once a day. A CAEN 4 channel high voltage supply (N495) will be used to supply HV for the drift chambers. The supply is capable of monitoring currents at the microamp level.describe gas used, HV, signal electronics
Cosmic tests
scope pulses
DAQ
describe the DAQ for measuring detector output
Electron test facility
IAC 25 MeV electron accelerator
secondary electron beam setup
Description of collimation system goes here as well as lead pencil target. Description of how beam size will be measured or why it isn't needed.