Difference between revisions of "TF Management"

From New IAC Wiki
Jump to navigation Jump to search
Line 2: Line 2:
  
 
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery.
 
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery.
 +
8/?/08: 2 Charge collectors arrives at ISU.  None were useful, CERN and I saw problems they will fix and send 2 more.
 
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension
 
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension
10/22/08: Charge collector arrives at ISU
+
10/22/08: Charge collector arrives at ISU (No output connectors so I had to send it back)
 
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant.
 
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant.
 
10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it
 
10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it

Revision as of 19:09, 24 January 2009

Timeline

7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. 8/?/08: 2 Charge collectors arrives at ISU. None were useful, CERN and I saw problems they will fix and send 2 more. 8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension 10/22/08: Charge collector arrives at ISU (No output connectors so I had to send it back) 10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant. 10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it 11/6/08 : after several exchanges a final invoice version (#5?) is sent to LaTech 11/19/08: Tony reports construction complete at Qweak collaboration meeting. Detector testing need to be done but due to LaTech's grant emergency only a HV test was completed. 11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.

1/12-15/08: Tony sends Greg 1/4 report suggesting that communication take place concerning the last R1 milestone delay 1/19/09: Klaus tells Greg that the last R1 milestone is delayed from March, 09 until Oct. 09. Tony has no idea where this number comes from and was never contacted for discussion. 1/20/09: Klaus submits critic of GEm construction to Greg Smith and the R1 work package leader 1/21/09: Greg e-mails an evaluation of Klaus' critics by an outside expert, 1/23/09: phone conference