Run Plan

  • Push dump magnet upstream as far as possible
  • Shield around it with lead as far downstream as possible.
  • Get a TOF spectrum with the D2O target. Set detector thresholds.
  • Verify that most of the photons, as measured by the neutrons from D2O and the pair spectrometer, are coming through the photon collimators. Do this by looking at both count rates for radiator in and photon hole blocked and unblocked.
  • Initiate studies of backgrounds, where “background” is defined as photons not coming from the radiator. Do radiator in/radiator out runs for beam on central position. Look at count rates for both neutrons from D2O and pair spectrometer.
  • Check for time stability of ratios of backgrounds to good stuff.
  • Do background studies (radiator in/out) for beam up and beam down.
  • Evaluate if hardener is useful. If so, optimize thickness.
  • Do D2O asymmetry measurements.