Met with Kelly Tremblay to discuss survey plans.  Goal is to be ready for Qweak collaborators and survey crew to align detector on June 4.  The "Fork" used to connect the GEM detector to the translator will be fiducialized for the laser survey system by mounting 4 targets on the fork.   
+
Met with Kelly Tremblay to discuss survey plans.  Goal is to be ready for Qweak collaborators and survey crew to align detector on June 4.  The "Fork" used to connect the GEM detector to the translator will be fiducialized for the laser survey system by mounting 4 targets on the fork.  The request is to have the "Y" location surveyed in to 100 microns (this is essentially <math>\theta</math>) We desire the The Z - location beam upstream/downstream is the least critical.
  
 
DAQ computer name is : cdaql6
 
DAQ computer name is : cdaql6

Revision as of 18:00, 13 May 2010

5/12/2010

Detector installation

The Qweak GEM detector has been installed in the doghouce in Hall-C and the HV was turned on. On the scope picture below is shown the GEM trigger out pulse, after it has been amplified and integrated with timing filter amplifier. The high voltage supply is placed in the doghouse with the other electronics.

GEMTrigOutinDoghouse-12-05-2010.jpgGEMTrigOutandGEMdetectorinDoghouse-12-05-2010.jpg

GEMSetUPinDoghouse-12-05-2010.jpg

Electronics

We have the NIM Bin with the following modules: Leading edge discriminator, timing filter amplifier(X2), Gumstix module.
GEMNIMBINandModulese-12-05-2010.jpgGEMGumstixandI2CNIMModuleinDoghouse-12-05-2010.jpg

Gas

The gas bottle filled with ArCO2 is placed outside the doghouse. We have two 90 ft shielded twisted ribbon cables next to region 1 area.


cables need to be routed about colimator 2.

GASbottleoutsidetheDoghouse-12-05-2010.jpgGEMShieldedRibbonCables-12-05-2010.jpg

5/13/2010

Met with Kelly Tremblay to discuss survey plans. Goal is to be ready for Qweak collaborators and survey crew to align detector on June 4. The "Fork" used to connect the GEM detector to the translator will be fiducialized for the laser survey system by mounting 4 targets on the fork. The request is to have the "Y" location surveyed in to 100 microns (this is essentially [math]\theta[/math]) . We desire the The Z - location beam upstream/downstream is the least critical.

DAQ computer name is : cdaql6


R1 ROC name : QWROC11