Qweak

From New IAC Wiki
Revision as of 18:13, 23 January 2011 by Foretony (talk | contribs) (→‎Hardware)
Jump to navigation Jump to search

Approved with A rating at JLAB for 198 "PAC" days at 150 [math]\mu[/math] A. The current [math]\Rightarrow[/math] need 223 "PAC" days for 5% measurment

Qweak wiki

hclog

Qweak_TaskList

Physics

Qweak_Delta

Qweak_R1_GEM_DNP2009

Normalization BPM response structure : https://qweak.jlab.org/elog/Beam/45

Hardware

Nauvoo: Missouri

Manasseh: 12th tribe


QweakGEMlocation 11-29-07.jpg side view QweakGEMlocation 11-29-07 SideView.jpg


Ionization Chamber

Readout Electronics
Qweak_Ionization Chamber

Qweak_Readout Electronics

Qweak_CAEN_HV

Rotator

Collimator

Software

Qweak online monitoring plots

http://qweak.jlab.org/onlineRegression/autoA/plots/


Qweak_Analysis_Software

Warren_Parsons_Log_Book

Qweak_V1495_FPGA_Programming

Qweak_R1_Software

Qweak_Qsqrd_Tracking

Qweak GEANT 4 Monte Carlo

Qweak GEANT3 Monte Carlo

Gumstix

Gumstix_Verdex

Gumstix_Installation

Qweak_flipbit

Management

Required Shifts

According to the Qweak shift policy of April 17, 2009:

"Set a goal for shifts to be staffed by institution, based on 30 shifts per collaborator at the institution, with the expectation that most institutions will provide more than this goal. "

Shift weights

One “Swing” shift (4pm-midnight) counts as 1.0 shifts: “Day” (8am-4pm) shifts count as 0.8 shifts, and “Owl” shifts (midnight-8am) count as 1.2 shifts towards the institutional goal.

Tforest shifts

Qweak shifts taken
Dates # of Shifts
Nov. 21-23, 2010 3
Dec. 13-17, 2010 5
Mar. 22-25, 2010 4

Total # of shifts = 12 Weighted # of shifts = 9.6 Shifts remaining: 20.4

Qweak_Installation

Qweak_Installation

Conference Call Number

Domestic Dial In Number: (800) 377-8846

Canada Dial In Number: (888) 276-7715

International Dial In Number (302) 709-8424

PARTICIPANT CODE: 08935091

Qweak thesis topics and students

http://qweak.jlab.org/doc-private/ShowDocument?docid=527

Qweak_R1_Proj_Management

Beam Tests

Readout tasks before beam test.

1.) Use the V1495 to record the VFAT test pattern

2.) create a method of displaying the hit pattern visually

3.) Adjust the VFAT threshold to determine noise level using cosmics, then repeat after installation in the HRRL experimental cell

4.) Determine if there are any clock frequency limitations to operation (too slow/too fast,...)

5.) Change VFAT threshold to determine dependence on hit pattern ionization radius.


HRRL_4-13-09

Commissioning

Qweak_Commissioning_6-2010

Talks

DNP_2009_R1_Talk

References

Qweak Related documents


R1 Bubbler Camera

Lee's Log book

Go Back User_talk:Tforest