Difference between revisions of "Qweak"

From New IAC Wiki
Jump to navigation Jump to search
 
(15 intermediate revisions by 2 users not shown)
Line 6: Line 6:
  
 
[[Qweak_TaskList]]
 
[[Qweak_TaskList]]
 +
 +
<pre>
 +
Complete work and be ready for beam before October 20, 2011. 
 +
 +
Drop Dead date is November 1.
 +
</pre>
  
 
=Physics=
 
=Physics=
 +
 +
dDelta letter of intent PAC25 2003
 +
 +
[[File:LOI-03-105.pdf ]]
 +
 
[[Qweak_Delta]]
 
[[Qweak_Delta]]
  
 
[[Qweak_R1_GEM_DNP2009]]
 
[[Qweak_R1_GEM_DNP2009]]
 +
 +
Normalization BPM response structure :  https://qweak.jlab.org/elog/Beam/45
  
 
=Hardware=
 
=Hardware=
Line 23: Line 36:
  
  
[[Ionization Chamber]]<br>
+
[[Qweak_Ionization Chamber]]<br>
  
[[Readout Electronics]] <br>
+
[[Qweak_Readout Electronics]] <br>
  
[[Rotator]]<br>
+
[[Qweak_CAEN_HV]]
  
[[Collimator]]<br>
+
 
 +
 
 +
[[Qweak_Rotator]]
 +
 
 +
 
 +
 
 +
[[Qweak_Collimator]]
 +
 
 +
 
 +
Collimator<br>
 +
 
 +
Rotator<br>
 +
Ionization Chamber
 +
 
 +
Readout Electronics
  
 
=Software=
 
=Software=
 +
 +
Qweak online monitoring plots
 +
 +
http://qweak.jlab.org/onlineRegression/autoA/plots/
 +
  
 
[[Qweak_Analysis_Software]]
 
[[Qweak_Analysis_Software]]
Line 63: Line 95:
 
"Set a goal for shifts to be staffed by institution, based on 30 shifts per collaborator at the  
 
"Set a goal for shifts to be staffed by institution, based on 30 shifts per collaborator at the  
 
institution, with the expectation that most institutions will provide more than this goal. "
 
institution, with the expectation that most institutions will provide more than this goal. "
 +
 +
===Shift weights===
 +
 +
One “Swing” shift (4pm-midnight) counts as 1.0 shifts: “Day” (8am-4pm) shifts count as 0.8 shifts, and “Owl” shifts
 +
(midnight-8am) count as 1.2 shifts towards the institutional goal.
  
 
===Tforest shifts===
 
===Tforest shifts===
  
#Dec13-17, 2010
+
Sign up using the link below
 +
 
 +
https://www1.jlab.org/mis/apps/physics/hallCShifts/index.cfm
 +
 
 +
{| border="1"  |cellpadding="20" cellspacing="0
 +
|colspan= "2" | Qweak shifts taken
 +
|-
 +
| Dates ||  # of Shifts
 +
|-
 +
|Nov. 21-23, 2010 || 3
 +
|-
 +
|Dec. 13-17, 2010 ||  5
 +
|-
 +
|Mar. 22-25, 2010 ||  4
 +
|}
 +
 
 +
Total # of shifts = 12
 +
Weighted # of shifts = 9.6
 +
Shifts remaining: 20.4
  
 +
30 shifts are expected
  
 
==Qweak_Installation==
 
==Qweak_Installation==
Line 117: Line 173:
 
=References=
 
=References=
 
[[Qweak Related documents]]
 
[[Qweak Related documents]]
 +
 +
 +
[https://hallcweb.jlab.org/cameras/R3_Bubblers/index.html R1 Bubbler Camera]
  
 
[http://www.jlab.org/~jhlee/nano/  Lee's Log book]
 
[http://www.jlab.org/~jhlee/nano/  Lee's Log book]
  
 
[http://wiki.iac.isu.edu/index.php/User_talk:Tforest Go Back] [[User_talk:Tforest]]
 
[http://wiki.iac.isu.edu/index.php/User_talk:Tforest Go Back] [[User_talk:Tforest]]

Latest revision as of 16:25, 2 October 2013

Approved with A rating at JLAB for 198 "PAC" days at 150 [math]\mu[/math] A. The current [math]\Rightarrow[/math] need 223 "PAC" days for 5% measurment

Qweak wiki

hclog

Qweak_TaskList

Complete work and be ready for beam before October 20, 2011.  

Drop Dead date is November 1.

Physics

dDelta letter of intent PAC25 2003

File:LOI-03-105.pdf

Qweak_Delta

Qweak_R1_GEM_DNP2009

Normalization BPM response structure : https://qweak.jlab.org/elog/Beam/45

Hardware

Nauvoo: Missouri

Manasseh: 12th tribe


QweakGEMlocation 11-29-07.jpg side view QweakGEMlocation 11-29-07 SideView.jpg


Qweak_Ionization Chamber

Qweak_Readout Electronics

Qweak_CAEN_HV


Qweak_Rotator


Qweak_Collimator


Collimator

Rotator
Ionization Chamber

Readout Electronics

Software

Qweak online monitoring plots

http://qweak.jlab.org/onlineRegression/autoA/plots/


Qweak_Analysis_Software

Warren_Parsons_Log_Book

Qweak_V1495_FPGA_Programming

Qweak_R1_Software

Qweak_Qsqrd_Tracking

Qweak GEANT 4 Monte Carlo

Qweak GEANT3 Monte Carlo

Gumstix

Gumstix_Verdex

Gumstix_Installation

Qweak_flipbit

Management

Required Shifts

According to the Qweak shift policy of April 17, 2009:

"Set a goal for shifts to be staffed by institution, based on 30 shifts per collaborator at the institution, with the expectation that most institutions will provide more than this goal. "

Shift weights

One “Swing” shift (4pm-midnight) counts as 1.0 shifts: “Day” (8am-4pm) shifts count as 0.8 shifts, and “Owl” shifts (midnight-8am) count as 1.2 shifts towards the institutional goal.

Tforest shifts

Sign up using the link below

https://www1.jlab.org/mis/apps/physics/hallCShifts/index.cfm

Qweak shifts taken
Dates # of Shifts
Nov. 21-23, 2010 3
Dec. 13-17, 2010 5
Mar. 22-25, 2010 4

Total # of shifts = 12 Weighted # of shifts = 9.6 Shifts remaining: 20.4

30 shifts are expected

Qweak_Installation

Qweak_Installation

Conference Call Number

Domestic Dial In Number: (800) 377-8846

Canada Dial In Number: (888) 276-7715

International Dial In Number (302) 709-8424

PARTICIPANT CODE: 08935091

Qweak thesis topics and students

http://qweak.jlab.org/doc-private/ShowDocument?docid=527

Qweak_R1_Proj_Management

Beam Tests

Readout tasks before beam test.

1.) Use the V1495 to record the VFAT test pattern

2.) create a method of displaying the hit pattern visually

3.) Adjust the VFAT threshold to determine noise level using cosmics, then repeat after installation in the HRRL experimental cell

4.) Determine if there are any clock frequency limitations to operation (too slow/too fast,...)

5.) Change VFAT threshold to determine dependence on hit pattern ionization radius.


HRRL_4-13-09

Commissioning

Qweak_Commissioning_6-2010

Talks

DNP_2009_R1_Talk

References

Qweak Related documents


R1 Bubbler Camera

Lee's Log book

Go Back User_talk:Tforest