Day 3. December 5, 2007. WEDNESDAY


Shift Personnel
Collaborator Shift
Amine 8-10 am , 2-5 pm
P. Bertan 8am - 5 pm
T. Forest 10 am - 2pm
P. Cole noon - 5pm
10 hours of beamtime

o Place Crystals 1, 2, 3, 4 on translator table.

   * Crystal 1:  2 hours
   * Crystal 2:  1 hours
   * Crystal 3:  1 hour
   * Crystal 4:  0.5 hours

o Transparency Measurement (~3 hours)

o Blue Light curing (24 hours)

o Place Crystals 5, 6, 7, 8 on translator table.

   * Crystal 5:  2 hours
   * Crystal 6:  1 hours
   * Crystal 7:  1 hour
   * Crystal 8:  0.5 hours

o Transparency Measurement (~3 hours)