Mallory Williams Schedule

From New IAC Wiki
Revision as of 21:10, 22 September 2011 by Foretony (talk | contribs) (Created page with ' {| border="1" |cellpadding="20" cellspacing="0 |- |Mon || Tues || Wed || Thurs || Fri |- | 5/17/10 || 9/30/10 || 8/6/10 ||Sign MOU |- | 5/17/10 ||9/30/11 || 4/12/11 || Co…')
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Mon Tues Wed Thurs Fri
5/17/10 9/30/10 8/6/10 Sign MOU
5/17/10 9/30/11 4/12/11 Contract recieved
8/3/2010 8/3/2010 Readiness Review
9/1/10 10/29/10 Hire and train R1 Lead Stringer
10/1/10 2/28/11 Hire and train 2 R1 stringers
11/16/09 11/30/10 Build R1 Cleanroom
11/5/2010 11/12/2011 Ship 1st R1 Box From JLab to ISU
12/17/2010 2/28/2011 String First R1 Chambers
2/21/2011 3/31/2011 Ship remaining R1 Boxes From JLab to ISU
7/13/12 Complete 6th R1 chamber
4/5/13 9/30/13 Ship chambers, fixtures, platforms and crane to JLab