Difference between revisions of "IAC LeadFlourideCherenkovCrystalTests 5-09"

From New IAC Wiki
Jump to navigation Jump to search
Line 54: Line 54:
  
 
==Day 3==
 
==Day 3==
 +
 +
;Accelerator Settings
 +
{| border="1"
 +
| beam energy || 20 MeV
 +
|-
 +
| Rep Rate: ||  30 Hz
 +
|-
 +
| I_peak:    || 60 mA/pulse
 +
|-
 +
| pulse width:|| 0.1 <math>\mu</math>s (100 ns)
 +
|-
 +
|}
 +
 
\multicolumn{2}{l}{Silicon test}\\
 
\multicolumn{2}{l}{Silicon test}\\
 
Irradiation {\bf batch \#2}\\
 
Irradiation {\bf batch \#2}\\
 
Bleaching of batch \#2:&38 hours\\
 
Bleaching of batch \#2:&38 hours\\
 
=
 
=
 +
 
== Day 4 ==
 
== Day 4 ==
 
Irradiation batch \#6:&4 new blocks\\
 
Irradiation batch \#6:&4 new blocks\\

Revision as of 16:14, 28 April 2009

http://clasweb.jlab.org/wiki/index.php/Hall_A_IAC_Tests


Previous Tests: IAC_LeadFlourideCherenkovCrystalTests

Run Plan

Summary

Task Time Budget
Beam setup 0.5 days
Testing 20 new blocks 2.5 days
Silicon test 1.0 day
Bleaching/Re-irradiation test 0.5-1 day
Testing old blocks 12 blocks/day


Accelerator Settings
beam energy 20 MeV
Rep Rate: 30 Hz
I_peak: 60 mA/pulse
pulse width: 0.1 [math]\mu[/math]s (100 ns)

Day 1

Beam setup & 2-3 hours\\ Irradiation batch \#1:&3 new blocks + 1 old ``reference block\\ Irradiation {\bf batch \#2}:&4 new blocks\\ Bleaching of batch \#2:&29 hours\\ Irradiation batch \#3:&4 new blocks\\


Day 2

Irradiation batch \#4:&4 new blocks\\ Irradiation batch \#5:&4 new blocks\\ Irradiation {\bf batch \#2}:&4 new blocks\\ Bleaching of batch \#2:&24 hours\\

Day 3

Accelerator Settings
beam energy 20 MeV
Rep Rate: 30 Hz
I_peak: 60 mA/pulse
pulse width: 0.1 [math]\mu[/math]s (100 ns)

\multicolumn{2}{l}{Silicon test}\\ Irradiation {\bf batch \#2}\\ Bleaching of batch \#2:&38 hours\\ =

Day 4

Irradiation batch \#6:&4 new blocks\\ Irradiation batch \#7:&4 new blocks\\ Irradiation batch \#8:&4 new blocks\\

Day 5

Irradiation {\bf batch \#2}\\ \multicolumn{2}{l}{Silicon test}\\ Day 6 -- Bleaching of batch \#2:&24h\\

5/11/09

Go back IAC_Experiments