HRRL July 2012Run

From New IAC Wiki
Jump to navigation Jump to search

Goals

measure the Beam spot size on target

Measure the Transmission

Measure Positrons produced

Runs

Setup

Detector2 (NaI-2 , S/N 60002-8292-I) is at beam left. It needs 1080 V. IAC_NaI_Detectors#Det2

Detector3 is at beam right. It needs 1060 V. IAC_NaI_Detectors#Det3

(When taking down the experiment It was observed that NaI-1, S/N 60002-8454-I was on the Beam right location).
NaI-3 was replaced with NaI-1 after run#3663. 

HRRL_Positrons_Jul_2012_Runs_Setup

T1 converter Target spec

0.04 inch = 1.016 mm: File:CHIPs T1 TungstenTargetMatCert 1mm.pdf CHIPs T1 TungstenTargetMatCert 1mm.png

In the second week we changed T2 to the same target as T1.

HRRL_Positrons_Jul_2012_Runs_Setup#Targets

Shieldings

hrrl_pos_jul2012_shieldings

What will I do if I run again

Improvements_HRRL_Positron_Runs_July_2012

Links

Dipole mapping: [[1]]

Positrons