CLAS 12 R1 Statement of Work (SoW)

Timeline

Construction Phases

Phase Start Date End Date Description
1 01/03/2011 02/31/2011 String half of the field wires in R1DCA
2 03/01/2011 05/31/2011 complete stringing of R1DCA, instrument and test R1DCA, begin R1DCB
3 05/01/2011 09/30/2011 String, instrument and test R1DCB
4 09/03/2011 12/21/2011 String, instrument and test R1DCC
5 01/03/2012 03/30/2012 String, instrument and test R1DCD
6 02/03/2012 06/29/2012 String, instrument and test R1DCE
7 03/30/2012 07/13/2012 String, instrument and test R1DCF

Hiring

Start Date End Date Position cost 21% Fringe 18% Overhead total
11/01/2010 10/31/2013 Lead Stringer 60,000/yr * 3 yrs = 180,000 37,800 32,400 250,200
01/03/2011 06/29/2012 Stringer 1 & 2 (A,B,D,F) $20/hr * 40 hr/week * 77 weeks =61,600 12,936 11,088 85,624
07/01/2011 08/03/2012 Stringer 3 & 4 (B,C,E) $20/hr * 40 hr/week * 54 weeks =43200 9072 7776 60,048
11/01/2010 07/30/2012 Technician 40,000/yr * 1.75 yr = 70,000 14,700 12,600 97,300
Current total
$493,172

Budget

Technicians

The stringing and testing of the R1 Drift chambers will require the hiring of 6 Technicians to string the Region 1 Drift Chambers. One technician, known as the "lead stringer", will be responsible for overseeing the remaining technicians, maintaining strict quality controls, updating progress reports, and working to solve problems which occur during the construction process. Four technicians will be hired at a cost of $20/hr which will be responsible for stringing the wires in the Drift chambers. The last technician will test wire tension, attach electronic boards, and provide support for the other technicians as needed..