Difference between revisions of "CLAS12 R1 SOW"

From New IAC Wiki
Jump to navigation Jump to search
Line 53: Line 53:
  
 
== Operating Costs==
 
== Operating Costs==
===Consumables===
+
===Equipment and Parts===
 
{| border="1"  |cellpadding="20" cellspacing="0  
 
{| border="1"  |cellpadding="20" cellspacing="0  
 
|-
 
|-
 
| Cost || Item
 
| Cost || Item
|-
 
| 5,000 || Clean room Frocks and Pants for 3 years
 
|-
 
| 800|| dedicated Clean room shoes for 4 stringers (stringers won't wear booties)
 
|-
 
| 500|| dedicated Clean room STEEL TOE shoes for 2 Riggers
 
|-
 
| 1,500 || Shoe covers for technicians, lead stringer, quality control inspector and other visitors
 
|-
 
| 2,304|| Head  covers for all personnel
 
|-
 
| 800 || Face masks for stringers and technicians
 
|-
 
| 2700 || Nitrile Gloves for 3 years
 
|-
 
| 4000 || Lint Free Clean room wipes  for 3 years
 
|-
 
| 1800 || Tacky Mates 3 locations  for 3 years
 
|-
 
| 500 || Tacky roller replacement heads used daily to clean floor  for 3 years
 
|-
 
| 1600|| Cleaning supplies, mops, buckets, solutions for 3 years
 
|-
 
| 952 || Hysol EA 9360 Epoxy
 
|-
 
| 1300|| Epon 826 Resin
 
|-
 
| 800|| Versamid 140 Hardener
 
|-
 
| 100|| Epoxy mixing supplies
 
|-
 
| 400|| Alcohol
 
|-
 
| 50|| Appllicator Rollers and putty knives
 
|-
 
| 400|| Glue Applicator Syringes, tips, plungers
 
|-
 
| 400|| Ultasonic Cleaner and solutions
 
 
|-
 
|-
 
| 125|| Gas bottle cart
 
| 125|| Gas bottle cart
|-
 
| 4500|| AR/CO2 gas bottles and rental fees for 3 years
 
 
|-
 
|-
 
| 1000|| Gas bottle regulators and hoses
 
| 1000|| Gas bottle regulators and hoses

Revision as of 17:09, 2 September 2010

CLAS 12 R1 Statement of Work (SoW)

Timeline

Construction Phases

Phase Start Date End Date Description
1 01/03/2011 02/31/2011 String half of the field wires in R1DCA
2 03/01/2011 05/31/2011 complete stringing of R1DCA, instrument and test R1DCA, begin R1DCB
3 05/01/2011 09/30/2011 String, instrument and test R1DCB, begin R1DCC
4 09/03/2011 12/21/2011 String, instrument and test R1DCC, begin R1DCD
5 01/03/2012 03/30/2012 String, instrument and test R1DCD, begin R1DCE
6 02/03/2012 06/29/2012 String, instrument and test R1DCE, begin R1DCF
7 03/30/2012 07/13/2012 String, instrument and test R1DCF

Hiring

Start Date End Date Position cost 21% Fringe 18% Overhead total
11/01/2010 10/31/2013 Lead Stringer 60,000/yr * 3 yrs = 180,000 37,800 32,400 250,200
01/03/2011 06/29/2012 Stringer 1 & 2 (A,C,E) 2 x ($20/hr * 40 hr/week * 83 weeks) =132,800 27,888 23,904 184,592
03/01/2011 08/03/2012 Stringer 3 & 4 (B,D,F) 2 x ($20/hr * 40 hr/week * 75 weeks) =120,000 25,200 21,600 166,800
11/01/2010 07/30/2012 Technician 40,000/yr * 92 weeks = 70,770 14,861 12,738 98,369
Current total
$699,961

Budget

Technicians

The stringing, instrumentation, and testing of the R1 Drift chambers will require the hiring of 6 technicians. One technician, known as the "lead stringer", will be responsible for overseeing the remaining technicians, maintaining strict quality controls, updating progress reports, working towards solving problems which occur during the construction process, and assist with the R1 installation at JLab. Four technicians will be hired at a cost of $20/hr which will be responsible for stringing the wires in the Drift chambers. The last technician will test wire tension, attach electronic boards, and provide support for the other technicians as needed.

The workforce will be deployed in 3 stages. The first stage will be to hire the lead stringer and technician. The lead stringer will be trained at JLab for at least 3 weeks in the art of stringing, instrumenting and testing CLAS12 drift chambers. A technician, whose has a supporting role in the process will spend at least 1 week being trained on the use of the tension measurement apparatus and instrumentation procedure. Once training is complete, the lead stringer will return to ISU and begin the hiring process for 2 stringers. The second stage will be the training of two stringers by the lead stringer as the first R1 drift chamber (R1DCA) is strung. The third stage will be to hire 2 more stringers who will be trained during the stringing of the second R1 drift chamber (R1DCB). We expect to be stringing 2 chambers at a time after the first group of stringers has strung half of the wires for R1DCA. The technician will be spot checking tension during the first stage. Since instrumentation requires substantially less time than stringing, our expectation is that the technician will spend some time supporting the string tension measurements as well as instrumenting and testing strung drift chambers.


Operating Costs

Equipment and Parts

Cost Item
125 Gas bottle cart
1000 Gas bottle regulators and hoses

Equipment

File:SOW V1.doc