Difference between revisions of "Beam Test Jul 5 2012"

From New IAC Wiki
Jump to navigation Jump to search
 
Line 402: Line 402:
 
= Camera Triggering =
 
= Camera Triggering =
  
Used Stanford pulser. External triggered by gun sync. Out put at "AB", "VAR". Cam trig sent from to "A_-_B".  
+
Used Stanford pulser. External triggered by gun sync. Out put at "AB", "VAR". Cam trig sent from to "A_-_B".  This works well at 30 reprate.
  
 
A = T + 2 micro second.
 
A = T + 2 micro second.
  
 
B = T + 11 micro second.
 
B = T + 11 micro second.

Latest revision as of 21:30, 8 July 2012

Vacuum Leak Issue

On Friday (29Jun2012) vacuum is at 23.5 mtorr.

Removed one problem gaskit, vacuum at 20 mtorr (with turbo on). The gaskit is at the end of the 45 deg bellow.

Fixed snapped bolt at the end of the 90 deg, with roughing pump, vacuum is 2.55 torr.

Check and Fix on Monday the July 2nd

Vacuum was fine until energy slits. We put blank-off after energy slits, then pulled the vacuum, vacuum pressure was low enough to light up the filament. This indicates energy slit is well sealed.

We pulled the vacuum just on 5-way cross without the top flag, and with short bellow and the short beam pipe myles made, there was a leak. Engineers suspects it was the pipe Myles made leaking. Kevin will redo the pipe.

We pulled the vacuum on 2nd dipole connected to 90 degree beam line until the end of 3rd triplet



Beampipe myles wielded was fixed, and placed to beamline fortesting by engineers. This beampipe was tested along with energy slits.

Vacuum wentdown to 8 mtorr range. When alcohol sprayed on the of the energy slits, there jump on the vacuum, then it was sealed with vacuum sealing liquid, vacuum went down to 4 mtorr.

It was suspected that energy Slits were the problem. End of Energy slits was sealed and tested, vacuum went down to lower ten to minus 5 torr range. Energy slits are good.

The gasket at the end of the energy slit were not well centered, and dent on the gasket was not good. So this could be the source of leak.

Test was also done on from 2nd dipole and 90 deg beam line until the end of the 3rd triplet, vacuum went down to 3 time 10 to the minus 5 torr.

5 way cross with flag on it along with Myles's pipe removed and Tested, vacuum went down to 3*10^(-5). The were good.

Myles's long beampipe that goes through the wall was tested, it went down to 2*10^(-5) torr. It was good.

Test was done all the beam parts except long beampipe goes through the wall. Vacuum went down till 3*10^(-5) torr range. Vacuum is good.

Conclusions

1. Major leak was on the beampipe made by Myles.

2. There are minor leaks with misplaced gaskets. One at the end of the 3rd triplet, one is at the end of 2nd dipole.

Later Observations

After 2hours the vacuum is down to 3*10^(-6) torr.

The next (July 3rd) day morning vacuum went down to 5*10^(-7) torr. Then turned up ion pump, left ion pump along with turbo. In the afternoon, sucking station removed, ion pump was pumping. The pressure was at 10^(-7) range.

On July 4th, the vacuum is at 5.6 * 10^(-7) range.

Preparation

[Check List]

1. Magnets: Hock up q7 and D2. Check Q8-11.

2. Camera: (a) Check if Working, shielding good, Sync? Cam 2 for 45 flag.

3. Flags: Hock up and check if working

4. Farady Cup: All 3 hocked up?

6. Gas bottle for valve full? --

7. Gas bottle for flags full? --

8. 3 Pickup Coils (Green Torroids):

9. Energy slit working?


Run Plan (Goal)

General goals are:

1. To find settings for different energies.

2. To find out each beam elements are working properly.

3. Deliver the beam to 0 degree, then 45 degree and 90 degree beamline. Observe them with Faraday cup at 0, 45 and 90 degrees and record settings.

Run list

Do the following for different energies. Start from 10 MeV, the do 3 MeV, then Do 15 MeV etc.

1. Deliver the beam to 0 degreebeamline

Use 0 deg Faraday cup to observe electron beam current.

2. Deliver the beam to 45 degree beamline

1. Observe the beam using Energy slits' two jaws.

2. Observe the beam using 45 degree Flag with YAG target.

3. Observe the beam using 45 deg Faraday cup.

4. Change the width of the slits and see the change in the slit jaw currents and 45 Faraday cup signals.

3. Deliver the beam to 90 degree beamline

Use 90 deg Faraday cup to observe electron beam current.


Energy Scan at 15 esh MeV

[Dipole Map]

1. Tuning

Energy Switch Out (High En Range)
Dipole Coil Current
e- Beam Energy () MeV (mapping )
Solenoid 1 12.9 A
Solenoid 2 13.7 A
Gun Hor 0.1 A
Gun Ver 0 A
Output Hor -0.5 A
Output Ver 0.0 A
Rep Rate 30
Gun HV 10(Knob Setting)
Gun Grid Voltage 7.24 (Knob Setting)
RF frequency 2856.291 MHz
Modulator HV Power Supply 4.84 (Knob Setting)
RF macro Pulse Length (FWHM) 200 ns
Q1 (A) 0
Q2 (A) 0
Q3 (A) 0
Q4 (A) 0
Q5 (A) 0
Q6 (A) 0
Peak Current on FC 1 ) 60 mAmps

Energy Scan at 8 MeV esh

1st Tune

Energy Switch Out (high En range)
Dipole Coil Current
nominal e- Beam Energy () MeV (mapping )
Solenoid 1 12.1 A
Solenoid 2 9.6 A
Gun Hor + 0.2 A
Gun Ver 0 A
Output Hor + 0.2 A
Output Ver + 0.1 A
Rep Rate 30
Gun HV 8.97(Knob Setting)
Gun Grid Voltage 9.96 (Knob Setting)
RF frequency 2856.289 MHz
Modulator HV Power Supply 4.185 (Knob Setting)
RF macro Pulse Length (FWHM) 200 ns
Q1 (A) 0
Q2 (A) 0
Q3 (A) 0
Q4 (A) 0
Q5 (A) 0
Q6 (A) 0

5.8 MeV ranghe

Energy switch is Out, linac operates at High energy

Energy Switch Out (High En Range)
nominal e- Beam Energy () MeV (mapping )
Solenoid 1 10.8 A
Solenoid 2 7.3 A
Gun Hor 0 A
Gun Ver 0 A
Output Hor + 0.1 A
Output Ver - 0.2 A
Rep Rate 3
Gun HV 10(Knob Setting)
Gun Grid Voltage 9.5 (Knob Setting)
RF frequency 2856.330 MHz
Modulator HV Power Supply 4.85 (Knob Setting)
RF macro Pulse Length (FWHM) 200 ns
Q1 (A) 2
Q2 (A) 4
Q3 (A) -1
Q4 (A) 1
Q5 (A) 0
Q6 (A) -1


D1 & D2 Current at FC 90 deg
10.6 Amps (5.7925 MeV) Hrrl pos Jul5 2012 beam to 90deg FC Dipoles10p6Amp.png
10.7 Amps (5.8481 MeV) Hrrl pos Jul5 2012 beam to 90deg FC Dipoles10p7Amp.png

Energy Scan at Low Energy 6.5610 MeV

2nd Tune

Energy switch is in, linac operates at low energy

Energy Switch In (Low En Range)
Dipole Coil Current
nominal e- Beam Energy () MeV (mapping )
Solenoid 1 10.1 A
Solenoid 2 9.6 A
Gun Hor 0 A
Gun Ver 0 A
Output Hor + 0.2 A
Output Ver + 0.1 A
Rep Rate 3
Gun HV 10(Knob Setting)
Gun Grid Voltage 9.5 (Knob Setting)
RF frequency 2856.617 MHz
Modulator HV Power Supply 3.97 (Knob Setting)
RF macro Pulse Length (FWHM) 200 ns
Q1 (A) +2.4
Q2 (A) +1
Q3 (A) -0.6
Q4 (A) -2.2
Q5 (A) + 2.8
Q6 (A) -1.2
Q7 (A) -4
Q8 (A) -4.9
Q9 (A) +5.5
Q10 (A) -4.8
D1 & D2 (A) 12


Q7 (Amps Current on 90 deg Faraday cup
0 Hrrl pos Jul5 2012 beam to 90deg FC Q7 0Amp.png
1 Hrrl pos Jul5 2012 beam to 90deg FC Q7 1Amp.png
2 Hrrl pos Jul5 2012 beam to 90deg FC Q7 2Amp.png
3 Hrrl pos Jul5 2012 beam to 90deg FC Q7 3Amp.png
5 Hrrl pos Jul5 2012 beam to 90deg FC Q7 5Amp.png

1. Tuning

Energy switch is in, linac operates at low energy

Energy Switch In (Low En Range)
Dipole Coil Current
nominal e- Beam Energy () 4 MeV (mapping )
Solenoid 1 3.5 A
Solenoid 2 10.6 A
Gun Hor 0.1 A
Gun Ver -0.3 A
Output Hor 0.1 A
Output Ver 0.1 A
Rep Rate 25
Gun HV 8.97(Knob Setting)
Gun Grid Voltage 9.96 (Knob Setting)
RF frequency 2856.730 MHz
Modulator HV Power Supply 3.96 (Knob Setting)
RF macro Pulse Length (FWHM) 200 ns
Q1 (A) 0
Q2 (A) 0
Q3 (A) 0
Q4 (A) 0
Q5 (A) 0
Q6 (A) 0
Scope on FC 1 34.2 mA 200 px
Scope on FC 2 200 px
Beam Spot 200 px

Deliver beam to the 90 FC

We were not able to deliver the beam to then end of the 90 deg beamline. We checked the hock-up of the 2nd dipole magnet, it was hocked up in a wrong way.

After we reconnected the dipole in the right way, we observed the beam at 90 deg Faraday cup.


At 8 MeV setting. I had 74 mA at FC1. After bending 45 I got 6 mA with Energy slits full open (3.44 cm). 6/74 = 8.1%.

Camera Triggering

Used Stanford pulser. External triggered by gun sync. Out put at "AB", "VAR". Cam trig sent from to "A_-_B". This works well at 30 reprate.

A = T + 2 micro second.

B = T + 11 micro second.