12/6/13

Goal: Ship 3 chambers to JLab (S5, S6, and S3 ) on Jan. 8, 2014

Ambition: ship S1 as well.


S3: stringing is done, one side is potted, last side in progress.

S2: now aligned to repair the last wires that are out of spec.

1 Pallet is assembled and ready for shipping, a second pallet is assemble but one boot remains to be installed.

Haitham has traced out dust covers for S5.

David - Finish potting S3 before Dec 9, install windows on S3 before Dec 16, move S3 to upper leave and have it crated by Dec 23, put S5 in its crate before Jan 6

Haitham - finish Q&A on S5 and then crate up S5

Derrick - Finish third pallet before Dec 16.


Trailer is 48 ft long.

Double check pallet length


CLAS12_R1_Progress_Reports#December_2013