7/2/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 91). Removed pretensioner C3 at row 88.

Strung 41 Field wires on Sector 6 (SL1 Fields are now complete). Removed pretensioner C7 at row 228.

Began visual inspection of Sector 6 before rotation.


7/3/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 103).

Completed visual inspection of Sector 6. Rotated chamber, leveled stringing machine, repositioned magnet and aligned chamber for stringing Sense wires in SL2.


7/5/12

Strung 42 Field wires on Sector 5 (now on SL2 - row 111). Removed pretensioner R3 at row 104.

Strung 25 Sense wires on Sector 6 (now on SL2 - row 12).

Completed weekly Tension Trend Tests for both Sector 5 and Sector 6.


7/9/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 121).

Strung 36 Sense wires on Sector 6 (now on SL2 - row 24).


7/11/12

Strung 98 Field wires on Sector 5 (now on SL2 - row 135).

Strung 18 Sense wires on Sector 6 (now on SL2 - row 30).


7/12/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 147). Removed R4 pretensioner at row 136.

Strung 48 Sense wires on Sector 6 (now on SL2 - row 46).

Completed Tension Trend tests for both Sector 5 and Sector 6 chambers.


7/16/12

Low temperature alarm was sounding upon arrival this morning. The temperature monitoring record shows a drop in temperature over the weekend that seems to coincide with a dramatic increase in humidity (Pocatello is currently experiencing uncharacteristically high humidity associated with rain and thunder showers). The temperature set point was increased to 69 degrees (per discussion with Dr. Forest). Stringing operations were haulted until temperatures began to stabilize. Temperatures declined again and the temperature set point was increased to 70 degrees. Temperatures seem to be holding between 68 and 69 degrees now.

After approximately 14:00, the humidity levels were above 55%. The humidity set point was lowered to 45% (per discussion with Dr. Forest). The humidity level immediately dropped and has not increased since the change.

While stringing operations were haulted, a clean was conducted in the cleanroom. After cleaning, particles were measured and were within specifications (0.5um = 11,700 particles per square meter and 5.0um = 1,650 particles per square meter).

Strung 56 Field wires on Sector 5 (now on SL2 - row 154). Removed C5 pretensioner at row 154.

Strung 48 Sense wires on Sector 6 (now on SL2 - row 62).