7/2/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 91). Removed pretensioner C3 at row 88.

Strung 41 Field wires on Sector 6 (SL1 Fields are now complete). Removed pretensioner C7 at row 228.

Began visual inspection of Sector 6 before rotation.


7/3/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 103).

Completed visual inspection of Sector 6. Rotated chamber, leveled stringing machine, repositioned magnet and aligned chamber for stringing Sense wires in SL2.


7/5/12

Strung 42 Field wires on Sector 5 (now on SL2 - row 111). Removed pretensioner R3 at row 104.

Strung 25 Sense wires on Sector 6 (now on SL2 - row 12).

Completed weekly Tension Trend Tests for both Sector 5 and Sector 6.


7/9/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 121).

Strung 36 Sense wires on Sector 6 (now on SL2 - row 24).


7/11/12

Strung 98 Field wires on Sector 5 (now on SL2 - row 135).

Strung 18 Sense wires on Sector 6 (now on SL2 - row 30).


7/12/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 147). Removed R4 pretensioner at row 136).

Strung 48 Sense wires on Sector 6 (now on SL2 - row 46).

Completed Tension Trend tests for both Sector 5 and Sector 6 chambers.