201110 R1ProgressRep

From New IAC Wiki
Revision as of 03:46, 13 October 2011 by Foretony (talk | contribs)
Jump to navigation Jump to search

10/3/11

124 guard wires were strung today.

10032011 CleanroomTemperature.png

10/4/11

100411 DFStringing1.jpg 100411 DFStringing2.jpg

90 guard wires were strung today.

All guard wires have been strung.

The chamber has been rotated and we will start stringing field wires tomorrow.

10042011 CleanroomTemperatures.png

10/5/11

48 field wires were strung today. Tension measurements were made for all of these wires also.

Temperature measurements are odd and are a concern. Will continue to monitor this. Possibly the heat created by the magnet and it's proximity to the temperature sensor?

10052011 CleanroomTemperatures.png

10/6/11

49 field wires were strung today as well as 8 redo's.

10062011 CleanroomTemperatures.png

10/7/11

10072011 Marcie Stringing.jpg 10072011 Mallory Stringing.jpg

63 wires were strung today.

10072011 CleanroomTemperatures.png

14:00 on the temperature graph is 8:00 AM.

CLAS12_R1_Progress_Reports