12/12/12
Worked on evaluating the background after the installation of 8" thick Pb wall in accelerator room and installing a FC, Scintillator, and Phosphorous screen at the end of the 90 degree line.
12/13/12
Worked on establishing a small spot size on the Phosphorous target and then documenting the beam properties.
12/14/12
Worked on establishing a small spot size on the Phosphorous target and then documenting the beam properties.