201209 R1ProgressRep
9/4/12
Strung 42 Field wires on Sector 5 (now on SL1 - row 152).
Strung 48 Sense wires on Sector 6 (now on SL1 - row 189).
The Physical Science building at ISU was evacuated at approximately 1pm by the fire and police departments after someone reported the smell of natural gas. A HAZMAT team was called in and the cause was found to be gases produced in a hood in the Chemistry Department. The hood had malfunctioned. We were evacuated until 5pm.
All wires on S6 were continuity tested. S5 will be tested tomorrow.
9/5/12
Strung 63 Field wires on Sector 5 (now on SL1 - row 161). Removed pretensioner C5 at row 160.
Strung 48 Sense wires on Sector 6 (now on SL1 - row 205).
All wires strung on S5 and S6 were continuity tested to check for crossed wires.
9/6/12
Strung 21 Field wires on Sector 5 (now on SL1 - row 164).
Strung 24 Sense wires on Sector 6 (now on SL1 - row 213).
All wires strung on S5 and S6 were continuity tested to check for crossed wires.
Tension Trend tests were completed for both Sector 5 and Sector 6 chambers.
A complete cleanroom wipedown and clean was performed at the end of the work day.
9/7/12
Replaced all ceiling filters.
9/10/12
Strung 48 Field wires on Sector 5 (now on SL1 - row 171).
Strung 42 Sense wires on Sector 6 (SL1 sense wires complete).
Began complete visual inspection of Sector 6 for potential repairs and replacements.
All wires strung on S5 and S6 were continuity tested to check for crossed wires.
- Sector 6 is now completely strung
9/11/12
Strung 49 Field wires on Sector 5 (now on SL1 - row 178). Removed pretensioner R5 at row 174.
Visual inspection of Sector 6 chamber, wires, crimp pins and feed throughs in preparation for feed through repair before potting.
All wires in SL1 and SL2 of Sector 6 have been tested to check for crossed wires.
9/12/12
Strung 49 Field wires on Sector 5 (now on SL1 - row 184).
Repositioned a few bent Field crimp pins on Sector 6. Retested tensions and replaced wires as necessary.
All wires strung today on Sector 5 were continuity tested for crossed wires.
9/13/12
Strung 28 Field wires on Sector 5 (now on SL1 - row 189).
All wires strung today on Sector 5 were continuity tested for crossed wires.
Removed and replaced 6 damaged feed throughs on Sector 6 (SL1 - bottom 2-5, 4-8 and 4-9. SL2 - bottom 222-5 and top 195-6 and 197-6). Pictures and a write up of the procedure used will be posted Monday.
Tension Trend tests were completed for both Sector 5 and Sector 6 chambers.
A weekly clean of the entire cleanroom was performed.
9/17/12
Strung 49 Fields on Sector 5 (now on SL1 - row 196).
Replaced 4 wires on Sector 6 and began final tension testing before potting on SL1.