201112 R1ProgressRep
Jump to navigation
Jump to search
12/1/11
91 wires were strung today.
12/2/11
97 wires were strung today. All field wires are strung and the final tensioner has been removed.
12/3/11
Weekly trend measurement was done today.
12/5/11
Prior to rotating the chamber, I decided to do a thorough visual inspection to ensure no crossed wires. During this inspection, several wires were found that had kinks in them. These wires were replaced. Tensions were measured also.
Chamber has been rotated. Sense wire stringing has begun.
22 sense wires were strung today.
12/6/11
84 sense wires were strung today.
12/7/11
45 sense wires were strung today.
12/8/11
72 sense wires were strung today.