HRRLPos Timeline Summary
Jump to navigation
Jump to search
| Completion Date | IAC | Task |
| 9/10 | 2 weeks ($10k) | Chad builds and installs stands |
| 10/10 | 2 days ($1k) | IAC engineers move HRRL to new location |
| 10/10 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
| 10/10 | 2 weeks ($10k) | IAC engineers install beam line with magnets |
| 11/9/10 | RF conditioning | |
| 11/2910-12/15/10 | NRF experiment with moved HRRL | |
| 2/16/11 | OTR test with beam | |
| 3/3/11 | OTR test with beam | |
| 3/14/11-3/18/11 | Sadiq emittance measurements. Beam misalignment was discovered. It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall). | |
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
| 3/11? | Sadiq and Khalid disassembles beam line for alignment | |
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 8/2011 | 1 week Mapped one Quad (Khalid, Sadiq) | |
| 8/2011 | 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | |
| 8/2011 | $500 | 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag installed |
| 10/2011 | 1 week Map 2nd Dipole (Khalid, Sadiq) | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
| 1/25/2012 | Target Tungsten disks | |
| 2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $66k
Indirects from DOE :
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.