| Completion Date | IAC | Task |
| 1/11? | 2 weeks ($10k) | IAC engineers install beam line |
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
| 4/18/2011 | 2 weeks ($10k) | Chad builds 4 stands |
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
| 1/25/2012 | Target Tungsten disks | |
| 2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $66k
Indirects from DOE :
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.