10/3/11
124 guard wires were strung today.
10/4/11
90 guard wires were strung today.
All guard wires have been strung.
The chamber has been rotated and we will start stringing field wires tomorrow.
10/5/11
48 field wires were strung today. Tension measurements were made for all of these wires also.
Temperature measurements are odd and are a concern. Will continue to monitor this. Possibly the heat created by the magnet and it's proximity to the temperature sensor?
10/6/11
49 field wires were strung today as well as 8 redo's.
10/7/11
63 wires were strung today.
14:00 on the temperature graph is 8:00 AM.