HRRL run on March 22-26 2010
Preliminary setup
3/17/10
Install detector infrastructure to mount 2 Drift chambers, 2 Scintillators and 1 GEM on a translator table.
Install collimation
3/18/10
Install all detectors and associated electronics (power supplies, cabling, gas lines,...)
3/19/10
install DAQ system and associated readout electronics.
Check channels in histograms
3/22/10
Final day for completing system checks
3/23/10
1pm - 5pm: Tune beam for low and high current