HRRL 4-13-09
Jump to navigation
Jump to search
Default HRRL running Conditions
run plan
Date | Task |
4/11/09 | Install Motion Sliders |
4/12/09 | Install DAQ and Drift chambers |
4/13/09 | Install Aluminum brick shutter and interlock with HRRL, test beam transport: Run HRRL accelerator from 3pm til 5 pm (25 ns pulse width, 3 MeV electrons, 1 Hz rep rate, 3 mA peak) |
4/14/09 | Run HRRL from 9 am til 5 pm (25 ns pulse width, 3 MeV electrons, 1 Hz rep rate, 3 mA peak), Do Plateau measurements and test readout |
4/15/09 | Run HRRL from 2 pm til 5 pm, position studies using Drift chamber and GEM |
4/16/09 | Run HRRL from 2 pm til 5 pm, efficiency tests |
4/17/09 | Run HRRL from 9 am til 5 pm finish detector tracking studies |