201209 R1ProgressRep

From New IAC Wiki
Revision as of 23:30, 6 September 2012 by Lewimar3 (talk | contribs) (→‎9/5/12)
Jump to navigation Jump to search

9/4/12

Strung 42 Field wires on Sector 5 (now on SL1 - row 152).

Strung 48 Sense wires on Sector 6 (now on SL1 - row 189).

The Physical Science building at ISU was evacuated at approximately 1pm by the fire and police departments after someone reported the smell of natural gas. A HAZMAT team was called in and the cause was found to be gases produced in a hood in the Chemistry Department. The hood had malfunctioned. We were evacuated until 5pm.

All wires on S6 were continuity tested. S5 will be tested tomorrow.


9/5/12

Strung 63 Field wires on Sector 5 (now on SL1 - row 161). Removed pretensioner C5 at row 160.

Strung 48 Sense wires on Sector 6 (now on SL1 - row 205).

All wires strung on S5 and S6 were continuity tested to check for crossed wires.

9/6/12