6/1/12

Strung 70 wires on Sector 6 (now on SL1 - row 111). Removed R3 pretensioner at row 110.

Changed Field wire at SL1-110-3 (switched from roll F23 to roll F27).

Adjusted alignment of Sector 6.

Completed weekly tension trend test.

6/4/12

New stringer started today. Began training with observation and reading stringing manual.

Strung 84 wires on Sector 6 (now on SL1 - row 123).

Adjusted alignment of Sector 6.

Fixed stringer on Sector 6. The rubber on the left roller had extended over the edge of the roller and was slowing rotation. Pushed rubber back onto the roller and tested for free rotation before resuming stringing.

Started alignment of Sector 5. This chamber didn't have any jam nuts on the struts. New jam nuts were purchased but only fit one strut. Nuts will be returned to check for defect or wrong thread type.


6/5/12

Finished aligning Sector 5. Corrected wire adapter on Sector 5 stringing machine (last stringer had used the Field adapter and the wire was not dispensing properly. The Guard adapter is now in place and the machine is working well).

Began stringing training on SL1 Guard wires on Sector 5. Strung 14 Guard wires (now on SL1 - row 11).

Strung 35 Field wires on Sector 6 (now on SL1 - row 128).

Temperature and Humidity values are not registering on the 'cacti' website.