201111 R1ProgressRep
11/1/11
70 wires were strung today. Our second stringer should be starting tomorrow.
11/2/11
91 wires were strung today.
11/3/11
The correct HVAC filters came in today. A clean filter was installed today at ~10 AM. A small rise in temperature can be seen in the temperature graph when this change was made.
77 wires were strung today.
11/4/11
91 wires were strung today.
All field wires are strung on SL2.
11/7/11
Spent the day visually inspecting for crossed wires. We should have the chamber rotated tomorrow and hopefully back to stringing later in the afternoon.
11/8/11
Chamber was rotated this morning.
We started stringing SL1 mid-afternoon. We only managed 50 wires today.
Temperature drop was caused by our power supply overheating. For future reference, don't exceed the rated 60 Amps of current...
11/9/11
I removed one of the covers for our large ducting in an attempt to get some air flow through the room (not the clean room). This appears to have changed the cyclic rate of our HVAC. Temperature min/max appears to have been unaffected.
The ducting cover will be put back in place tomorrow.
63 wires were strung today.
11/10/11
63 wires were strung today.
Keeping the duct cover off until tomorrow.