HRRLPos Timeline Summary

From New IAC Wiki
Revision as of 17:19, 17 October 2011 by Foretony (talk | contribs)
Jump to navigation Jump to search
Completion Date IAC Task
9/10 2 weeks ($10k) Chad builds and installs stands
10/10 2 days ($1k) IAC engineers move HRRL to new location
10/10 2 weeks ($10 k) Built beam pipe and flanges (Kevin?)
10/10 2 weeks ($10k) IAC engineers install beam line with magnets
11/9/10 RF conditioning
11/2910-12/15/10 NRF experiment with moved HRRL
2/16/11 OTR test with beam
3/3/11 OTR test with beam
3/14/11-3/18/11 Sadiq emittance measurements. Beam misalignment was discovered. It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall).
7/2011 3 days ($1k) Removed and reinstall Gun for alignment (Chad)
3/11? Sadiq and Khalid disassembles beam line for alignment
3/30/11 Order Gate Valve (4 week lead time)
4/4/11 Complete Beam Line CAD drawing (J. Ellis)
8/2011 1 week Mapped one Quad (Khalid, Sadiq)
8/2011 3 weeks Zero degree beam line aligned (Khalid, Sadiq)
8/2011 $500 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag installed
10/2011 1 week Map 2nd Dipole (Khalid, Sadiq)
1/25/2012 Target Motor from Empire Magnetics
1/25/2012 1 week ($5k) Target Chamber design (IAC engineer)
1/25/2012 Target Tungsten disks
2009-2012 $30 k 3 weeks of beam time

IAC investment: $67.5k

Indirects from DOE : $90k

IAC personnel salary paid : $80k

Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.

Positrons#HRRL_beam_Line_installation