HRRL BeamLine 2011
Beam Line installation 2011
Timeline
| Completion Date | Task |
| 3/30/11 | Order Gate Valve (4 week lead time) |
| 4/4/11 | Complete Beam Line CAD drawing |
| 4/11/2011 | Built beam pipe and flanges (Kevin?) |
| 4/18/2011 | Complete Stands |
| 4/25/2011 | Built target chamber |