CLAS12 R1 SOW

From New IAC Wiki
Revision as of 16:29, 18 August 2010 by Oborn (talk | contribs) (→‎Stringers)
Jump to navigation Jump to search

CLAS 12 R1 Statement of Work (SoW)

Timeline

Phase Start Date End Date Description
12/17/2010 2/28/2011 String First R1 Chambers
2/21/2011 3/31/2011 Ship remaining R1 Boxes From JLab to ISU
7/13/12 Complete 6th R1 chamber
4/5/13 9/30/13 Ship chambers, fixtures, platforms and crane to JLab


Budget

Stringers

The stringing and testing of the R1 Drift chambers will require the hiring of 6 Technicians to string the Region 1 Drift Chambers. One technician, known as the "lead stringer", will be responsible for overseeing the remaining technicians, updating progress reports, and working to solve problems which occur during the construction process. Four technicians will be hired at a cost of $20/hr which will be responsible for stringing the wires in the Drift chambers. The last technician will test wire tension, attach electronic boards, and provide support for the other technicians as needed..

Technicians

CLAS12_R1