HRRL run on March 22-26 2010

Preliminary setup

3/17/10

Install detector infrastructure to mount 2 Drift chambers, 2 Scintillators and 1 GEM on a translator table.

Install collimation

3/18/10

Install all detectors and associated electronics (power supplies, cabling, gas lines,...)

3/19/10

install DAQ system and associated readout electronics.

Check channels in histograms

3/22/10

Final day for completing system checks

3/23/10

1pm - 5pm: Tune beam for low and high current

3/24/10

Positron spectrometer run plan

Detector tracking run plan