HRRLPos Timeline Summary
Jump to navigation
Jump to search
| Completion Date | IAC | Task |
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
| 4/18/2011 | 2 weeks ($10k) | Chad builds 4 stands |
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
| 1/25/2012 | Target Tungsten disks |
IAC investment: $26k
Indirects from DOE :
Although not requested, magnet power supplies and a LabView control interface were installed by Chad.