HRRLPos Timeline Summary
Jump to navigation
Jump to search
Completion Date | Task |
3/30/11 | Order Gate Valve (4 week lead time) |
4/4/11 | Complete Beam Line CAD drawing |
4/11/2011 | Built beam pipe and flanges (Kevin?) |
4/18/2011 | Chad builds X stands |
7/2011 | Removed Gun for alignment (Chad) |
8/2011 | Zero degree beam line aligned (Khalid, Sadiq) |
1/25/2012 | Target Motor from Empire Magnetics |
1/25/2012 | Target Chamber |
1/25/2012 | Target Tungsten disks |