CLAS 12 R1 Statement of Work (SoW)

Timeline

Phase Start Date End Date Description
12/17/2010 2/28/2011 String First R1 Chambers
2/21/2011 3/31/2011 Ship remaining R1 Boxes From JLab to ISU
7/13/12 Complete 6th R1 chamber
4/5/13 9/30/13 Ship chambers, fixtures, platforms and crane to JLab


Budget

Stringers

Technicians to string the Region 1 Drift Chambers will be hired at a cost of $20/hr.

Technicians