HRRL 4-13-09
Default HRRL running Conditions
Pulse Width | Rep Rate | Energy | |
8 mA | 25 ns | 1 Hz | 3 MeV |
run plan
Date | Task |
4/11/09 | Vaho stil running til 7 pm, configure Motion Sliders |
4/12/09 | Build shutter and unstack beam line |
4/13/09 | Install Aluminum brick shutter and interlock with HRRL, test beam transport: Run HRRL accelerator from 3pm til 5 pm (25 ns pulse width, 3 MeV electrons, 1 Hz rep rate, 8 mA peak) |
4/14/09 | Repair Freon leak in Chiller, HRRL down, Install DAQ |
4/15/09 | Run HRRL from 9 am til 5 pm (25 ns pulse width, 3 MeV electrons, 1 Hz rep rate, 8 mA peak), Do Plateau measurements and test readout |
4/16/09 | Run HRRL from 2 pm til 5 pm, position studies using Drift chamber and GEM |
4/17/09 | Run HRRL from 2 pm til 5 pm, efficiency tests |
4/20/09 | Run HRRL from 9 am til 5 pm finish detector tracking studies |
4/13/09
Electron Dose tests
Shutter In
0.1 mrad/hr outside HRRL experimental door.
2.7 mrad/hr in the end of HRRL experimental hallway.
Shutter Out
0.1 mrad/hr in Dr. Forest office.
Sintillator tests
RS1 = 2 aluminum blocks are in front of Long BLue Scintillator plugged into the cable patch pannel 223A2
FS1 = Small scintillator is in 223A1
HV SC1 | HV RS1 | Desc. |
840 | 840 |
GEM noise
100 ns RF pulse width
GEM in Accelerator room
Bag | Rep Rate | Current | Peak to peak noise |
Off | 990 Hz | 3 V =60 mA | 4 mV on 1 mus scale |
on + Ground strap | 990 Hz | 3 V =60 mA | 4 mV on 1 mus scale |
on No Ground strap | 990 Hz | 3 V =60 mA | 4 mV on 1 mus scale |