| Date |
Task
|
| 4/11/09 |
Install Motion Sliders
|
| 4/12/09 |
Install DAQ and Drift chambers
|
| 4/13/09 |
Install Aluminum brick shutter and interlock with HRRL, test beam transport: Run HRRL accelerator from 3pm til 5 pm (25 ns pulse width, 3 MeV electrons, 1 Hz rep rate, 3 mA peak)
|
| 4/14/09 |
Run HRRL from 9 am til 5 pm (25 ns pulse width, 3 MeV electrons, 1 Hz rep rate, 3 mA peak), Do Plateau measurements and test readout
|
| 4/15/09 |
Run HRRL from 2 pm til 5 pm, position studies using Drift chamber and GEM
|
| 4/16/09 |
Run HRRL from 2 pm til 5 pm, efficiency tests
|
| 4/17/09 |
Run HRRL from 9 am til 5 pm finish detector tracking studies
|