CH PAS Master Timeline
Jump to navigation
Jump to search
Timeline
This page will be used to document when each task is completed as a master reference for all work logged in the wiki. The plan is to make things easier when I need to pull things in the future.
May
5/10/21
- Attended intern orientation for first day at INL
- Completed training this week as well as began NaI plateau setup
5/18/21
- Began data collection for NaI plateau and operating point measurements
- Began writing analysis code for NaI plateau measurements
June
6/8/21
- Finished collection and analysis of NaI detector plateau measurements
6/9/21
- Began data colleciton for He3 Borated Poly attenuation study
6/11/21
- Finished data collection for He3 Borated Poly attenuation study
- Began writing analysis code for Borated Poly attenuation study
6/22/21
- Finished writing analysis code for He3 Borated Poly attenuation measurements and submitted plot to Paul
6/25/21
- Began BorAl attenuation measurements including overnight background runs