CH PAS Master Timeline
Jump to navigation
Jump to search
Timeline
This page will be used to document when each task is completed as a master reference for all work logged in the wiki. The plan is to make things easier when I need to pull things in the future.
May
5/10/21
Attended intern orientation for first day at INL
June
6/22/21
- Finished writing analysis code for He3 Borated Poly attenuation measurements and submitted plot to Paul
6/25/21
- Began BorAl attenuation measurements including overnight background runs