Sector 1 - began training stringers to turn on high voltage and look for signals using STB probe and ADB monitoring system.
 
Sector 1 - began training stringers to turn on high voltage and look for signals using STB probe and ADB monitoring system.
 +
 +
=10/02/12=
 +
 +
Sector 5 - removed and replaced 4 more damaged or glue contaminated feed throughs that were found during visual inspection (SL1: 16-2 (Sense). SL2: 37-1 (Guard), 227-8 (Field) and 227-9 (Field)).
 +
 +
Sector 6 - tested SL2 Field wires from row 169 to 189 (147 wires).
 +
 +
Injected a 10 MHz square wave with a 40 mV peak-peak amplitude into each channel of the ADB monitoring system. Tested the gain on A and B of each channel. Preliminary results show 5 channels that may not be functioning properly.
 +
 +
Temperatures in the cleanroom have been decreasing slowly over the last week. Increased the temperature set point of the HVAC system by one degree to keep temperatures within cleanroom specifications. Will monitor and report any issues.

Revision as of 21:10, 2 October 2012

10/01/12

Sector 6 - tested SL2 Field wires from row 134 to 168 (245 wires).

Sector 5 - restrung Guard and Field wires for replaced feed throughs in SL1 (Fields: 167-11, 187-2, 223-8 and 225-11. Guards: 227-10 and 228-3). All wires strung were continuity tested for potential crossed wires.

Sector 1 - began training stringers to turn on high voltage and look for signals using STB probe and ADB monitoring system.

10/02/12

Sector 5 - removed and replaced 4 more damaged or glue contaminated feed throughs that were found during visual inspection (SL1: 16-2 (Sense). SL2: 37-1 (Guard), 227-8 (Field) and 227-9 (Field)).

Sector 6 - tested SL2 Field wires from row 169 to 189 (147 wires).

Injected a 10 MHz square wave with a 40 mV peak-peak amplitude into each channel of the ADB monitoring system. Tested the gain on A and B of each channel. Preliminary results show 5 channels that may not be functioning properly.

Temperatures in the cleanroom have been decreasing slowly over the last week. Increased the temperature set point of the HVAC system by one degree to keep temperatures within cleanroom specifications. Will monitor and report any issues.