(Created page with '=7/2/12= Strung 84 Field wires on Sector 5 (now on SL2 - row 91). Removed pretensioner C3 at row 88. Strung 41 Field wires on Sector 6 (SL1 Fields are now complete). Removed pr…')
 
Line 6: Line 6:
  
 
Began visual inspection of Sector 6 before rotation.
 
Began visual inspection of Sector 6 before rotation.
 +
 +
 +
=7/3/12=
 +
 +
Strung 84 Field wires on Sector 5 (now on SL2 - row 103).
 +
 +
Completed visual inspection of Sector 6. Rotated chamber, leveled stringing machine, repositioned magnet and aligned chamber for stringing Sense wires in SL2.

Revision as of 23:37, 3 July 2012

7/2/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 91). Removed pretensioner C3 at row 88.

Strung 41 Field wires on Sector 6 (SL1 Fields are now complete). Removed pretensioner C7 at row 228.

Began visual inspection of Sector 6 before rotation.


7/3/12

Strung 84 Field wires on Sector 5 (now on SL2 - row 103).

Completed visual inspection of Sector 6. Rotated chamber, leveled stringing machine, repositioned magnet and aligned chamber for stringing Sense wires in SL2.