Difference between revisions of "201205 R1ProgressRep"
Line 76: | Line 76: | ||
Replaced furnace filter. | Replaced furnace filter. | ||
+ | |||
+ | |||
+ | =5/16/12= | ||
+ | |||
+ | Rotated Chamber 6 to Superlayer 1. Moved magnet cable to appropriate position. Leveled stringing arm. Aligned chamber for stringing Fields tomorrow. | ||
+ | |||
+ | Rotated Chamber 5 to Superlayer 1. Moved magnet cable to appropriate position. Leveled stringing arm. Will align chamber for stringing Guards tomorrow. | ||
+ | |||
+ | Wiped down dry shower plastic panels. |
Revision as of 21:54, 16 May 2012
5/1/12
Strung 84 Field wires on Chamber 6.
Strung 48 Guard wires on Chamber 5.
5/2/12
Strung 98 Field wires on Chamber 6.
Strung 35 Guard wires on Chamber 5.
5/3/12
Strung 84 Field wires on Chamber 6 (Now on row 181).
Strung 45 Guard wires on Chamber 5 (Now on row 123).
5/4/12
Strung 39 Guard wires on Chamber 5 (Now on row 162).
5/7/12
Strung 63 Field wires on Chamber 6 (Now on row 191).
5/8/12
Strung 56 Field wires on Chamber 6 (Now on row 200).
5/9/12
Strung 49 Field wires on Chamber 6 (Now on row 208).
Strung 13 Guard wires on Chamber 5 (Now on row 176).
5/10/12
Strung 63 Field wires on Chamber 6 (Now on row 217).
Strung 35 Guard wires in Chamber 5 (Now on row 211).
5/11/12
Strung 14 Field wires on Chamber 6 (Now on row 219).
Strung 23 Guard wires on Chamber 5 (Superlayer 2 complete).
Soldered and repaired 16 stringing chains.
Completed weekly trend test on Chamber 6.
5/14/12
Strung 63 Field wires on Chamber 6. (Superlayer 2 complete.)
Completed visual inspection of Chamber 6 Field wires.
Completed visual inspection of Chamber 5 Guard wires.
The railing on the upper floor was installed today. A particle count was run after completion and before stringing operations continued. The results were as follows: 0.5 micron = 11,500 / cubic meter 5.0 micron = 824 / cubic meter
5/15/12
Completed testing of all wires adjacent to wires that have been restrung. From now on, this task will be completed on the day that wires are restrung.
Replaced furnace filter.
5/16/12
Rotated Chamber 6 to Superlayer 1. Moved magnet cable to appropriate position. Leveled stringing arm. Aligned chamber for stringing Fields tomorrow.
Rotated Chamber 5 to Superlayer 1. Moved magnet cable to appropriate position. Leveled stringing arm. Will align chamber for stringing Guards tomorrow.
Wiped down dry shower plastic panels.