Difference between revisions of "201205 R1ProgressRep"
(→5/9/12) |
|||
Line 45: | Line 45: | ||
Strung 35 Guard wires in Chamber 5 (Now on row 211). | Strung 35 Guard wires in Chamber 5 (Now on row 211). | ||
+ | |||
+ | |||
+ | =5/11/12= | ||
+ | |||
+ | Strung 14 Field wires on Chamber 6 (Now on row 219). | ||
+ | |||
+ | Strung 23 Guard wires on Chamber 5 (Superlayer 2 complete). | ||
+ | |||
+ | Soldered and repaired 16 stringing chains. |
Revision as of 21:40, 11 May 2012
5/1/12
Strung 84 Field wires on Chamber 6.
Strung 48 Guard wires on Chamber 5.
5/2/12
Strung 98 Field wires on Chamber 6.
Strung 35 Guard wires on Chamber 5.
5/3/12
Strung 84 Field wires on Chamber 6 (Now on row 181).
Strung 45 Guard wires on Chamber 5 (Now on row 123).
5/4/12
Strung 39 Guard wires on Chamber 5 (Now on row 162).
5/7/12
Strung 63 Field wires on Chamber 6 (Now on row 191).
5/8/12
Strung 56 Field wires on Chamber 6 (Now on row 200).
5/9/12
Strung 49 Field wires on Chamber 6 (Now on row 208).
Strung 13 Guard wires on Chamber 5 (Now on row 176).
5/10/12
Strung 63 Field wires on Chamber 6 (Now on row 217).
Strung 35 Guard wires in Chamber 5 (Now on row 211).
5/11/12
Strung 14 Field wires on Chamber 6 (Now on row 219).
Strung 23 Guard wires on Chamber 5 (Superlayer 2 complete).
Soldered and repaired 16 stringing chains.