Difference between revisions of "201112 R1ProgressRep"
m (→12/13/11) |
m (→12/14/11) |
||
Line 61: | Line 61: | ||
84 sense wires were strung today. | 84 sense wires were strung today. | ||
− | + | =12/15/11= | |
+ | |||
+ | The installation of the large roll up doors began today. The scheduled completion of the doors is on Tuesday, December 20th. Stringing has been suspended until the doors have been installed. |
Revision as of 23:04, 15 December 2011
12/1/11
91 wires were strung today.
12/2/11
97 wires were strung today. All field wires are strung and the final tensioner has been removed.
12/3/11
Weekly trend measurement was done today.
12/5/11
Prior to rotating the chamber, I decided to do a thorough visual inspection to ensure no crossed wires. During this inspection, several wires were found that had kinks in them. These wires were replaced. Tensions were measured also.
Chamber has been rotated. Sense wire stringing has begun.
22 sense wires were strung today.
12/6/11
84 sense wires were strung today.
12/7/11
45 sense wires were strung today.
12/8/11
72 sense wires were strung today.
12/9/11
42 sense wires were strung today.
12/12/11
48 sense wires were strung today.
12/13/11
84 sense wires were strung today.
12/14/11
84 sense wires were strung today.
12/15/11
The installation of the large roll up doors began today. The scheduled completion of the doors is on Tuesday, December 20th. Stringing has been suspended until the doors have been installed.